User Acceptance test

Definition

 A lightweight UAT approach has been taken with UG. CAM have tested the brd line by line and any issues reported in JIRA. All issues are now closed https://www.jira.is.ed.ac.uk/jira/issues/?jql=project%20%3D%20SSG002

 

Roles and Responsibilities

 

Role

Responsibilities

Name

Project Manager

·         Communication with the Business Assurance Coordinator to agree format and scope of UAT

·        

 Maurice Franceschi

Testers

·         Execute tests from examining brd

-          link to jira  

 Ailsa Vamplew

 

Test Requirements

    • UAT completed 22 April 13
    • UAT took place in CAM premiises in Forrest Road
    • Testers tested brd line by line
    • No support was required from project services
    • UAT participants conducted the tests and recorded results in JIRA

 

Test Participants

 

Testing participants include representative from all areas involved in the solution. Testers and their specific areas of focus are identified in the table below: 

 

Name

Area Represented

Testing Area of Responsibility

 Ailsa Vamplew

CAM

 UG

 

Project Info

Not available.

Documentation

Not available.