Report for January 2020

Report Date
January 2020

Achievements in last period

  • Project Manager assigned end of January
  • Project initiated and initial meetings held to agree the scope 30-Jan.

Issues

  • No issues to report.

Next Steps

  • Complete planning phase and sign off the project brief

Milestones

 

Milestone Date
Planning -Brief 28-Feb-2020
Delivery 15-May-2020
Closure 15-Jun-2020
Project Status
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info