Report for January 2020
- Report Date
- January 2020
Achievements since last report
- Project brief approval and submission to Applications WIS
- Pre work for test environment upgrade, set up of test PCs
- Test plan created
- Data refresh from Live to Test
- Communications around submission of Timesheets
- Application upgrade to v14.03 completed in Test environment, sanity checking completed
- Operating System and SQL upgrade in progress
Issues
- Confirmation Elecosoft costs confirmed by project sponsor to be paid separately to consultancy work
- Outstanding timesheets is a key risk to upgrade of both test and live, concerns raised with numbers of timesheets outstanding in SEP PMO. Following positive discussion and effort from both SEP PMO and ISG PMO all outstanding timesheets were submitted for deadline
Next Steps
- Operating System and SQL upgrade to be completed in Test
- UAT to commence from 10th February
- Update of TAD
- Acceptance sign off
- Preparations for Live upgrade :
- Communications
- Go CAB
- IS Alert
The project status is GREEN
Application and Server upgrade completed in Test | 31-Jan-2020 |
User Acceptance Testing starts | 10-Feb-2020 |
User Acceptance Testing complete | 06-Mar-2020 |
Acceptance Sign off | 13-Mar-2020 |
Application and Server upgrade completed in Live | 19-Mar-2020 |
Client Rollout Complete | 26-Mar-2020 |
Deployment Review Sign Off | 02-Apr-2020 |
Closure | 16-Apr-2020 |
- Approved budget
- 100.0 days
- Activity this month
- 0.6 days
- Activity this year
- 12.9 days
- Activity to date
- 12.9 days
- Estimate to complete current year
- 79.0 days
- Estimate to complete future years
- 0.0 days