w/c 20th January 2020

  • Go-Live Preparations
    • GoCab paperwork submitted for go-live on 5th February
    • Request to Applications Management to commence Deployment CheckList 
    • Request for Technology Management  resource to complete Deployment CheckList 
  • piccl submitted to WIS re revised dates and budget 
  • User Acceptance Testing 
    • UAT Status schedule prepared 
    • UAT commencing 
    • Review of outstanding JIRAs undertaken with the business and the suppler
  • Risk Log updated
  • SSO
    • Certificate for live environment received and forwarded onto Dev Tech
  • Secure database access requirements forwarded onto Hope Park
  • Conference call notes, whilst reviewing outstanding JIRAs
    • Issues

      • Bugs would have to be resolved prior to the go-live
      • Requirements associated with field changes, moving fields, renaming labels, assigning default values to drop downs would be recognised as being in scope and would be applied if time available
      • Additional requirements and new reports would be deemed out of scope of the project and would require to be actioned under future support arrangements
  • SalesAgility

    • Technical Lead has returned to assist with any technical issues
    • An additional developer has been assigned to the project
  • Next Review

    • Scheduled for Wednesday 29th January, 3.00 p.m. – Supplier to organise a GoTo meeting