Report for December 2019

Report Date
December 2019

Achievements in last period

  • Meetings have been set up in January with key stakeholders to determine project scope

Issues

  • None this month

Next Steps

  • Business case completed 
  • Asta request form submitted to initiate project

 

 

Milestones

Milestones have not yet been determined - this will be done as part of the business case

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days