- Report Date
- December 2019
Achievements
- Server installed in Argyle House Media Studio
- Date for KB installation provisionally agreed 22/23 January
- Service Level Agreement signed and submitted to Editshare
- Initial meeting held with Studio Manager and Project Sponsor to outline ‘protocols’ work
Issues and changes
Next steps
- Jigsaw to deliver staff training on 17 January
- Confirm KB installation date
- Install backup server in KB
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days