Report for January 2020 (Interim)

Report Date
January 2020

Achievements this period

  • RED development resourcing issue which was the result from a conflict with SAS020 has now been resolved. Resource has been assigned to commence the development iterations from 03/02/2020.
  • Milestones have been agreed and set

Issues

  • None

Next Steps

  • Brief signoff can now be achieved
  • Foundation iteration meeting to prepare for Iteration 1 to start 

Milestones

Planning sign off 17-Jan-2020
Foundation complete 31-Jan-2020
Iteration 1 complete 21-Feb-2020
Iteration 2 complete 20-Mar-2020
Iteration 3 complete 17-Apr-2020
Iteration 4 (maintenance) complete 01-May-2020
Deploy to LIVE 05-May-2020
Closure 15-May-2020
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.