Report for December 19

Report Date
December 2019

Achievements in last period

  • Stefan Kaempf confirmed as project sponsor

Issues

  • None this month

Next Steps

  • First draft of brief to be circulated and team brought together to discuss

 

Milestones

Plan

13-Jan-2020

Deliver

31-Mar-2021

Close

15-Apr-2021

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
150.0 days
Activity this month
0.0 days
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
98.0 days
Estimate to complete future years
52.0 days