Report for December 2019

Report Date
December 2019

Resource Position

 

 

Forward Look

 

 

 

 

Section 2: Projects Not Started

Project Info

Programme Managers Commentary

FIN131 (AP90-002) Pension Scheme Changes 

The Pension Scheme changes project are potentially delayed until next year (2020/21)

  • Formal signoff is required first
  • Clarity is required from Payroll on scope for the project. 
    • If the project is sizeable there will be risks in relation to Finance / Payroll staff availability due to Core deployment commitments.  

FIN130 (AP90-001) Essential Updates to Finance Systems for Security

This project will now be initiated in February.  A review of scope will be undertaken to ensure the project is still required and that scope contains only business critical / security / legislative deployments (which cant be undertaken through support).

 

 

Section 3: Projects in Progress

 

Project Info

Project Managers Commentary

 

FIN119 (AP67-024)

eInvoicing

Core Funded

 

Milestones:

 

Milestone Due Date
Project closure TBC

 

RAG Status : RED

 

Report By Emma McNab for November 2019

Achievements this Period

  • Work to progress closure 
  • Review of remaining JIRA 

Issues

  • Though Finance Staff Resource has been maintained throughout, this risk remains AMBER until the Project is closed as Finance staff potentially have increased commitments to the CORE Programme.

  • The availability of the Project Manager and the  wider project team has resulted in an estimated 8 week slippage to closure. 

Next Steps

  • Finalise Draft Closure Report
  • Agree Project Sign Off / Closure

FIN126

Core Funded

Essential Finance System Compliance Updates and Document Revitalisation

 

Milestones:

Proposed milestones are:

Stage Milestone Due Date Complete   
Plan

 (A) Signed Letter of engagement

20-March-2019  Yes
Plan  Planning Complete (Project Brief) 03-May-2019  Yes
Analyse     (B) Business Analysis Complete          07-June-2019  Yes
Execute  (A) Completion of For:sight Proof of Concept phase 27-Sept-2019  Yes
Analyse  Re-Planning Post Compliance (Phase (B)) Scoping 19-July-2019  Yes
Build  (B) Build Complete 13-Sept-2019  Yes
Accept  (B) Acceptance Testing Complete 27-Sept-2019  Yes
Deliver  (A) Purchase of Arkk, For:sight bridging software 25-Oct-2019  Withdrawn
Deliver  (B) Deploy to Live 18-Oct-2019  Yes
Close  Project Closure 31-Oct-2019  No

 

RAG Status: RED

 

Report By Ken Miller for December 2019

Achievements in Last Period:

Work Stream (A)

  • End-to-end Dual run of VAT return via For:sight for last quarters VAT return successfully carried out.  
  • Progress of PoC phase of project through to sign off.
  • Review meeting agreed that purchase of the live solution would be outside the scope of tis project. 

Work Stream (B)

  • Carry out review of post go live issues and review lesson's learned.

Issues:

  • (A) There remains a small manual element to the MTD process which may make it non MTD compliant.  In particular the figures for boxes 2 and 9 of the VAT return will need to be manually submitted with the assistance of the For:sight tool.  This risk has raised with the UoE Tax Office and they have agreed that they are the owner of this risk.

Next Steps:

Work Stream (A)

  • Project closure tasks including addressing outstanding jira's.

Work Stream (A & B)

  • Project Closure

FIN127

Finance General Data Protection Regulation (GDPR)

Core Funded

Milestones

Milestone Due Date Complete  
Planning 01-Feb-2019  Yes
Analysis 03-May-2019  No
Solution Options 07-Jun-2019  No
Implementation Plan 28-Jun-2019  No
Delivery 30-Sep-2019  No
Closure 28-Oct-2019  No

 

RAG Status : RED

 

 

 

Report By Emma McNab for November 2019

Achievements in Last Period:

  • Analysis ongoing to confirm system owners and Finance responsibility with regards GDPR data compliance.

Issues

  • The revised number of systems that fall within the scope of the project means that once confirmed the project timescales will have to be re-estimated.
  • As a result of increased number of projects in scope it is proposed that projects identified to be replaced by the Core system will not be analysed with regards their GDPR requirements.
  • The Business Analyst has resigned and there is no available resource at this time to replace.  Resource issues have been escalated to Deputy CIO. 
  • The Project Manager is overallocated and unable to provide the required level of resource to the project.  
  • The wider Project Teams availability is poor given wider priorities in Finance.

Next Steps

  • Finalise projects that should be in scope of project.

  • Revised project scope for sign off by the Project Sponsor.

  • For systems not in scope but containing Finance data, contact system owners to confirm responsibility for GDPR compliance.

  • Re-planning meeting  required to review confirmed scope and to confirm revised schedule and tasks to be carried out under this project.

 

 

FIN128

FPM Upgrade

Core Funded

Milestones

Milestone Due Date
Acceptance Testing Complete       15-11-2019
Delivery Complete  25-11-2019
Project Closure  06-12-2019

 

 RAG Status : GREEN

 

 

Report By Kevin Hone for November 2019

Achievements in Last Period:

  • User Acceptance Testing is complete.
  • Preparations have been made for project implementation.
  • Agreement reached across the project team on a go-live date of the 10th December.

Issues:

  • Go-CAB had approved of a go-live on the 12th December but due to non-availability of internal and 3rd party staff, the date has provisionally been revised.
  • Lack of resource due to strike action means that a final confirmation date for implementation will not be until the first week of December.

Next Steps:

  • Confirm deployment and then move to DSOR and project closure.

FIN132

HR and Payroll Annual Maintenance 19/20

Core Funded

Milestones

Stage Milestone Due Date
Execute Start Security Patches 04-Feb-2020
Execute Phase 1 - RUP12 + any pre-requisites 04-Feb-2020
Execute Phase 1 - Deployment Signoff 25-Feb-2020
Execute Phase 2 - TYE + other statutory requirements (MAJOR) 03-Mar-2020
Execute Phase 2 - Deployment Signoff 25-Mar-2020
Execute Phase 3 - Post Budget 02-Jun-2020
Execute End Clones 26-Jun-2020
Close Close (MAJOR) 09-Jul-2020

RAG Status : GREEN

 

Report By Anne Mathison for December 2019

 

Achievements

  • Started Security Patches work
  • Completed in HRDEV Security patches - IS Apps
  • Completed in HRDEV Rapid Clone patch - IS Apps
  • Completed HRDEV Phase 1 RUP12 patches - IS Apps
  • Progressed & Completed HRDEV Security patches testing - HR, Payroll
  • Progressed & Completed HRDEV Rapid Clone patch testing - HR, Payroll
  • Progressed & Completed HRDEV Phase 1 RUP12 patches testing - HR, Payroll

Issues

  • None

Next Steps

  • Complete in HRTEST Security patches - IS Apps
  • Complete in HRTEST Rapid Clone patch - IS Apps
  • Complete HRTEST Phase 1 RUP12 patches - IS Apps
  • Progress & Complete HRTEST Security patches testing, Rapid Clone patch testing + Phase 1 RUP12 patches testing - HR, Payroll

Project RAG status of GREEN

Section 4: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

FIN118 (AP56-016)

eFinancials upgrade

 

Closure Report

FIN123 (AP56-016)

Annual Finance Document Revitalisation 17/18

Closure Report

FIN125

Media Production for Annual Report and Accounts    

Closure Report

FIN133

Corporate Planner Upgrade 

Closure Report
Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
Yes
Escalated to
Programme Sponsor
RAG Commentary
Resource continues to be an issue across the programme across project services and with Finance due to workloads and wider priorities. The Programme Manager continues to work with Programme Sponsor and Service Leads to progress contingency actions and escalate risks and issues as appropriate.