RAG Status : RED
|
Report By Emma McNab for November 2019
Achievements this Period
- Work to progress closure
- Review of remaining JIRA
Issues
-
Though Finance Staff Resource has been maintained throughout, this risk remains AMBER until the Project is closed as Finance staff potentially have increased commitments to the CORE Programme.
-
The availability of the Project Manager and the wider project team has resulted in an estimated 8 week slippage to closure.
Next Steps
- Finalise Draft Closure Report
- Agree Project Sign Off / Closure
`
|
FIN126
Core Funded
Essential Finance System Compliance Updates and Document Revitalisation
Milestones:
Proposed milestones are:
Stage |
Milestone |
Due Date |
Complete |
Plan |
(A) Signed Letter of engagement
|
20-March-2019 |
Yes |
Plan |
Planning Complete (Project Brief) |
03-May-2019 |
Yes |
Analyse |
(B) Business Analysis Complete |
07-June-2019 |
Yes |
Execute |
(A) Completion of For:sight Proof of Concept phase |
27-Sept-2019 |
Yes |
Analyse |
Re-Planning Post Compliance (Phase (B)) Scoping |
19-July-2019 |
Yes |
Build |
(B) Build Complete |
13-Sept-2019 |
Yes |
Accept |
(B) Acceptance Testing Complete |
27-Sept-2019 |
Yes |
Deliver |
(A) Purchase of Arkk, For:sight bridging software |
25-Oct-2019 |
Withdrawn |
Deliver |
(B) Deploy to Live |
18-Oct-2019 |
Yes |
Close |
Project Closure |
31-Oct-2019 |
No |
RAG Status: RED
|
- Report By Ken Miller for December 2019
Achievements in Last Period:
Work Stream (A)
- End-to-end Dual run of VAT return via For:sight for last quarters VAT return successfully carried out.
- Progress of PoC phase of project through to sign off.
- Review meeting agreed that purchase of the live solution would be outside the scope of tis project.
Work Stream (B)
- Carry out review of post go live issues and review lesson's learned.
Issues:
- (A) There remains a small manual element to the MTD process which may make it non MTD compliant. In particular the figures for boxes 2 and 9 of the VAT return will need to be manually submitted with the assistance of the For:sight tool. This risk has raised with the UoE Tax Office and they have agreed that they are the owner of this risk.
Next Steps:
Work Stream (A)
- Project closure tasks including addressing outstanding jira's.
Work Stream (A & B)
|
FIN127
Finance General Data Protection Regulation (GDPR)
Core Funded
Milestones
RAG Status : RED
|
Report By Emma McNab for November 2019
Achievements in Last Period:
Issues
- The revised number of systems that fall within the scope of the project means that once confirmed the project timescales will have to be re-estimated.
- As a result of increased number of projects in scope it is proposed that projects identified to be replaced by the Core system will not be analysed with regards their GDPR requirements.
- The Business Analyst has resigned and there is no available resource at this time to replace. Resource issues have been escalated to Deputy CIO.
- The Project Manager is overallocated and unable to provide the required level of resource to the project.
- The wider Project Teams availability is poor given wider priorities in Finance.
Next Steps
-
Finalise projects that should be in scope of project.
-
Revised project scope for sign off by the Project Sponsor.
-
For systems not in scope but containing Finance data, contact system owners to confirm responsibility for GDPR compliance.
-
Re-planning meeting required to review confirmed scope and to confirm revised schedule and tasks to be carried out under this project.
|
FIN128
FPM Upgrade
Core Funded
Milestones
RAG Status : GREEN
|
Report By Kevin Hone for November 2019
Achievements in Last Period:
- User Acceptance Testing is complete.
- Preparations have been made for project implementation.
- Agreement reached across the project team on a go-live date of the 10th December.
Issues:
- Go-CAB had approved of a go-live on the 12th December but due to non-availability of internal and 3rd party staff, the date has provisionally been revised.
- Lack of resource due to strike action means that a final confirmation date for implementation will not be until the first week of December.
Next Steps:
- Confirm deployment and then move to DSOR and project closure.
|
FIN132
HR and Payroll Annual Maintenance 19/20
Core Funded
Milestones
RAG Status : GREEN
|
Report By Anne Mathison for December 2019
Achievements
- Started Security Patches work
- Completed in HRDEV Security patches - IS Apps
- Completed in HRDEV Rapid Clone patch - IS Apps
- Completed HRDEV Phase 1 RUP12 patches - IS Apps
- Progressed & Completed HRDEV Security patches testing - HR, Payroll
- Progressed & Completed HRDEV Rapid Clone patch testing - HR, Payroll
- Progressed & Completed HRDEV Phase 1 RUP12 patches testing - HR, Payroll
Issues
Next Steps
- Complete in HRTEST Security patches - IS Apps
- Complete in HRTEST Rapid Clone patch - IS Apps
- Complete HRTEST Phase 1 RUP12 patches - IS Apps
- Progress & Complete HRTEST Security patches testing, Rapid Clone patch testing + Phase 1 RUP12 patches testing - HR, Payroll
Project RAG status of GREEN
|