December 2019 Monthly Project Report

Report Date
December 2019

Achievements

  • Completed Sentry upgrade
  • Delivered Sentry upgrade  

Issues

  • No issues

Next Steps

  • Meeting with project sponsor to agree sequence of Development tools upgrades plans
  • Replan development tools upgrades as agreed
  • P2 to migrate puppet master 4 to puppet master 5 is likely to start early this year
    • Dates to be agreed

 

Green RAG status this month

Milestones

 

Stage Milestone Due Date
Execute P2- Migrate puppet master 4 to puppet master 5 17-Feb-2020
Execute P3 Puppet - test and fix puppet master 5 04-Mar-2020
Deliver P3 Puppet library code master 5 delivered 19-Mar-2020
Execute Python Acceptance Tested 27-Mar-2020
Deliver Python Delivered 08-Apr-2020
Deliver Oracle Grid Delivered 21-May-2020
Execute Bamboo Acceptance Tested 29-May-2020
Deliver Bamboo Delivered 11-Jun-2020
Execute Nexus Updated 16-Jun-2020
Deliver Nexus Delivered 25-Jun-2020
Execute Overall Acceptance Milestone 02-Jul-2020
Deliver Overall Deployment Signoff 24-Jul-2020
Close Close 31-Jul-2020
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
155.0 days
Activity this month
3.0 days
Activity this year
21.0 days
Activity to date
21.0 days
Estimate to complete current year
134.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation