Report for December 2019

Report Date
December 2019

Achievements this period

  • An agreement has been reached on how to proceed with the database upgrade and the Mobile App upgrade. The Mobile upgrade has been delayed until mid January, so EST126 is proceeding to have DEV upgraded and signed off by 20/01/2020.
  • Milestone replan completed
  • Resources re-assigned for a January 2020 start on DEV

Issues

  • None

Next Steps

  • Complete the DEV upgrade to Oracle 12.2
  • Test and sign off DEV
  • Begin the TEST upgrade to Oracle 12.2

Milestones

DEV Upgrade Complete 20-Jan-2020
TEST Upgrade Complete 21-Feb-2020
UAT Complete 12-Mar-2020
LIVE Upgrade Complete 16-Mar-2020
DSOR 30-Mar-2020
Closure 08-Apr-2020
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
Milestones revised due to Estates Mobile App installation by Mass now taking place 21st / 22nd January.
Activity
Approved budget
69.0 days
Activity this month
5.0 days
Activity this year
26.0 days
Activity to date
26.0 days
Estimate to complete current year
41.0 days
Estimate to complete future years
0.0 days

Project Info

Not available.

Documentation

Not available.