Report for December 2019

Report Date
December 2019

Achievements

  • Planned a governance meeting in early January 

Issues

  • No issues

Next Steps

  • Project team to discuss options with Students Association to agree how to have more student engagement  in semester 2
  • Track the weekly usage of the pilot in Learn and Teams in semester 2
  • Students Association to ask the reps to seed the discussion with questions or updates
  • Agree revised suspension date with project team in January
  • Agree with project team when the evaluation will take place

 

Stage Milestone Date
Execute Suspension of Project 24-Jan-2020
Execute Unsuspend 22-May-2020
Execute Semester 2 Pilot End 05-Jun-2020
Deliver Deliver Report recommendations 12-Jun-2020
Deliver Sign off Report recommendations (Major) 19-Jun-2020
Close Closure of Project (Major) 30-Jun-2020
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Extra costs because project was not suspended. More effort required to promote student engagement.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
1.0 day
Activity this year
13.0 days
Activity to date
24.0 days
Estimate to complete current year
14.0 days
Estimate to complete future years
0.0 days