(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Karen Howie
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Projects in Progress:
TEL052 QMP Upgrade
TEL057 Learn Foundations
TEL058 Learn to the Cloud
TEL063 Lynda.com upgrade to Linkedin Learning
TEL064 Moodle Annual Upgrade 19/20
Forward Look and RAG

Resource Summary

Section Two: Projects Not Started
None
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||
|
QMP Upgrade (17/18) Compliance Milestones RAG Status: |
Report by Colin Watt for Dec 2019 Achievements in Last Period Issues Next Steps |
||||||
|
Learn Foundations Discretionary Milestones RAG Status: |
Report by Lee-Ann Simpson for Dec 2019 Achievements in the last period Issues Next Steps |
||||||
|
Learn to the Cloud Discretionary Milestones
RAG Status: GREEN |
Report by Karen Beggs for Dec 2019 Achievements in Last Period
Issues
Next Steps
|
||||||
|
Lynda.com upgrade to Linkedin Learning Compliance Milestones:
RAG Status: RED |
Report by Kevin Hone for Dec 2019 Achievements in Last Period
Issues
Next Steps
The project currently remains at Red but with a meeting in diaries for early January to bring together resource from both the business and technology in an effort to plan next steps to a resolution. Questions need to be resolved over (1) which data feed solution best fits the needs of the university and (2) who is to do the work and when? Answers to the latter, affecting time and possibly cost.
|
||||||
|
Moodle Upgrade Compliance Milestones: (to be agreed in planning stage)
RAG Status: GREEN |
Report by Colin Watt for Dec 2019 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Moodle Upgrade |
Closure Approved 16/08/19 |
|
Learn Upgrade |
Closure Approved 16/08/19 |
|
Academic Blogging Service |
Closure Approved 08/11/19 |
| Attachment | Size |
|---|---|
| 174.2 KB | |
| 160.28 KB | |
| 183.98 KB | |
| 148.08 KB | |
| 183.98 KB | |
| 148.08 KB | |
| 174.58 KB | |
| 150.37 KB | |
| 200.65 KB | |
| 153.52 KB | |
| 156.62 KB | |
| 160.05 KB |