Report for Nov 2019
- Report Date
- November 2019
Achievements this period
- Sprint 5 completed - HR - Access layer prototype , Estates UAT re-work
- Sprint 6 started - Access layer basic star schema / connection to BI Tools
- Git / Bamboo - Synch between DEV and TEST has been done for Foundation layer
Issues
- Git / Bamboo - Synch to LIVE requires a couple of scripts to be run in LIVE - delayed due to change freeze for the strike
- Budget will need to be increased - 253 days has been spent from initial allocation of 300 days and this is for the load of historic legacy data before the new core data is loaded
Next Steps
- Full backlog to be collected for the HR datamart
- Complete Sprint 6
- Plan Sprint 7
- Alpha release to LIVE
- Approved budget
- 300.0 days
- Activity this month
- 44.0 days
- Activity this year
- 212.0 days
- Activity to date
- 253.0 days
- Estimate to complete current year
- 280.0 days
- Estimate to complete future years
- 0.0 days