Report for Nov 2019

Report Date
November 2019

Achievements this period

  • Limited progress - limited business resources while the Exams team focus on prep for the Dec 2019 exam diet
  • Bug fixing  and upgrade of Exam Web Timetables to new version of  Python 3.6, Django 2.2 is in progress

Issues

  • Slow performance in LIVE is being investigated by the IS Production
  • Pending changes in Exam Scheduler Connect in TEST haven't yet been tested by the Exam business team  
  • Resource conflict for Project Manager with TTU017 Course Timetabling Scientia Upgrade

Next Steps

  • WP2 - Exam team complete testing of Student system connector changes ( expect  Dec 2019 earliest?) 
  • WP3 - project team continue working through the 10 JIRAS carried over from SAS005
  • WP2 - deploy to LIVE during Jan 2020, ahead of start of scheduling of April / May exam diet 
Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
GREEN
Overall
RED
RAG Commentary
RED Issue - Time - WP2 not yet tested by Exams team - missed milestone - narrow window to deploy the Connect changes to LIVE before start of scheduling for next Exam diet in Jan 2020. Project Manager has had limited time to push this forward while focusing on the TTU017 Course Timetabling Scientia Upgrade, and Exams team are focused on the prep for the Dec 2019 exam diet
Change Status
Time
Moderate
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
WP2 testing delayed
Activity
Approved budget
25.0 days
Activity this month
2.7 days
Activity this year
15.0 days
Activity to date
16.3 days
Estimate to complete current year
8.5 days
Estimate to complete future years
0.0 days