- Report Date
- November 2019
Achievements in Last Period:
- v5.16.1 was deployed to the development environment.
- Initial meeting attended to consider future use of a cloud portal.
Issues:
- No forward plan to compensate for loss of the Project Manager in January (reason for reporting a RAG status of RED).
Next Steps:
- Preparations for deployment of v5.16.2 to the development environment with work to be undertaken by alternative resource.
- Further discussions to be had with the 3rd party Elsevier on the use of a cloud portal.
- Approved budget
- 50.0 days
- Activity this month
- 2.5 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 40.0 days
- Estimate to complete future years
- 0.0 days