Report for November 2019

Report Date
November 2019

Achievements this period

  • Impact assessment call with Mass carried out, and confirmation that Archibus is compatible with the Oracle 12c upgrade.
  • Estates have secured dates with Mass for the mobile app install to DEV and TEST for 17th and 18th December 2019. The project can continue and plan around those dates.

Issues

  • The recommendation by the EST126 technical team and EST126 project and programme manager was to allow EST126 to progress first followed by the Mobile app install. This was so that the testing of each application can be isolated and carried out without interference of the other project, Also allowing EST126 to go first would mean that TEST and LIVE environments would be the same and the mobile app can be deployed after the database upgrade as it would be more prone to bugs and fixes required. Despite the recommendations, Estates have booked Mass to come in on the 17th and 18th so this increases risk on the project for testing and deployment.
  • Due to the delay in getting agreement on the Mobile Application installation, the milestones will need to be replanned.

Next Steps

  • Milestone replan for project. This will now begin with the DEV migration in January 2020

Milestones

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue: Discussions with Estates during November to get an agreement on an upgrade plan that encompasses the Mobile App development (Estate's project) and this Archibus database upgrade has resulted in the delay in starting the DEV upgrade. Estates want both to be run in tandem with the mobile app deployed to DEV and TEST first. Impact: The technical team have indicated a bigger risk with the Mobile App being deployed first regarding testing and final deployment. Resolved, business accept the greater risks. DEV upgrade to commence in January
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor, Senior Supplier, Programme Manager
Activity
Approved budget
69.0 days
Activity this month
6.0 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
50.0 days
Estimate to complete future years
0.0 days