Report for November 2019
- Report Date
- November 2019
Report for November 2019 by Ken Miller
Achievements
- Work on overall implementation plan in conjunction with Fivium to schedule resource.
- Continue internal process regarding case migration to the replacement eCase.
- Procurement and Legal both approved project to progress to contract review.
- Fivium drafting initial G-Cloud call-off contract prior to review.
Issues
- Delay in procurement process is delaying fully engaging with Fivium in the technical aspects of the transition process. Project has now been re-assigned to our third UoE procurement contact this year.
- Overall project delay will mean that the milestones need to be revised once implementation plan has been agreed.
Next Steps
- Progress with Procurement and Fivium regarding contract review and sign off.
- Work on overall implementation plan in conjunction with Fivium to schedule resource.
- Engagement with Fivium regarding case migration process to the replacement eCase.
Milestones
Rescheduled dates yet to be approved by WIS are:
Target Date![]() |
Title | Stage |
---|---|---|
21-May-2019 | Go/No Go Budget Approval | Plan |
26-Jul-2019 | End of Planning | Plan |
26-Jul-2019 | Product Evaluation | Analyse |
30-Aug-2019 | Product Procurement | Procure |
25-Oct-2019 | Product Implementation | Build |
08-Nov-2019 | User Acceptance Testing - Sign Off | Accept |
22-Nov-2019 | Go Live | Deliver |
06-Dec-2019 | Deployment Sign Off | Deliver |
13-Dec-2019 | Migration of Historic Data | Deliver |
13-Dec-2019 | Legacy ColdFusion Decommissioned | Deliver |
20-Dec-2019 | Project Closure | Close |
- Approved budget
- 100.0 days
- Activity this month
- 6.0 days
- Activity this year
- 19.7 days
- Activity to date
- 42.8 days
- Estimate to complete current year
- 63.0 days
- Estimate to complete future years
- 0.0 days