Report for November 19
- Report Date
- November 2019
Achievements in last period
- Start of project approved at WIS 8 November
- PM kicked off project familiarisation with programme manager and PM from the initial analysis project
Issues
- Alistair Fenemore unaware he was project sponsor. Escalated to programme manager
- End of planning date moved from 6 Dec 19 to 13 Jan 20 due to additional PM work on INF135 and new project USG014 whose procurement will take up time in December not anticipated when this projects dates were submitted.
Next Steps
- First draft of brief to be circulated and team brought together to discuss
Milestones
Plan |
13-Jan-2020 |
Deliver |
31-Mar-2021 |
Close |
15-Apr-2021 |
- Approved budget
- 150.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.0 day
- Activity to date
- 1.0 day
- Estimate to complete current year
- 135.0 days
- Estimate to complete future years
- 14.0 days