Report for November 2019

Report Date
November 2019

Achievements in this Period

  • Delivery and Closure milestones rescheduled to accommodate re-work and user testing availability
  • Analysis and re-work completed to resolve issue (JIRA MVM132-3)
  • Report in LIVE and shared with user to checkĀ 

Issues

  • None

Next Steps

  • Completion of user checks on LIVE report
  • Closure

Milestones

Stage Milestone Due Date Previous Date Complete
Deliver Delivery of reports complete 29-Nov-2019 14-Oct-2019 No
Close Close report complete and approved 20-Dec-2019 15-Nov-2019 No
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Project progressing to plan
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Change Commentary
Slight delay to delivery and therefore closure milestones was approved to accommodate user's availability to test in LIve
Activity
Approved budget
42.0 days
Activity this month
1.6 days
Activity this year
7.7 days
Activity to date
19.3 days
Estimate to complete current year
21.0 days
Estimate to complete future years
0.0 days