w/c 25th November 2019

  • DSOR 
    • Unable to sign-off DSOR at this time as further work is required on the OLA.  Once completed, (scheduled for 29/11/19), Production will then sign-off DSOR 
  • Project Closure 
    • Approved by the project team 
    • Currently awaiting approval from Production and the Senior Supplier
    • Due to the above, the project closure has been withdrawn from WIS this week and will be re-submitted next week
  • Supplier Support 
    • The project team have confirmed that support can now be handed over to the supplier support team