- Report Date
- November 2019
Work completed
- Milestones approved by Project Board on 20th November - Project Planning stage and Confirm priority order for module migration
- The Project Board approved the Working Group's recommendation to use WordPress (not drupal, as per original plan)
- Investigation into WordPress capability to deliver certificates after completion of eLearning modules is almost complete. eForms plug-in provides 90% of functionality required. Final testing needed to identify how final 10% can be delivered.
- Temp appointed to complete the full audit of all content on STARs (Core Competencies), STARs (Advancing Modules) and HEARTe Platforms. Start date 3rd December
- Test module migration is in progress
- Transfer of domains & certificates to CHSS scheduled for January
Issues
None
What's next
- Complete full audit
- Complete test migration
- Confirm if additional development time will be needed for certificates functionality
- Review timelines using data gathered during audit and test migration
- Recruitment of additional content developer for six months
- Next Working Group meeting 10th December
- Next Project Board meeting 19th December
- Approved budget
- 110.0 days
- Activity this month
- 7.0 days
- Activity this year
- 11.0 days
- Activity to date
- 11.0 days
- Estimate to complete current year
- 99.0 days
- Estimate to complete future years