w/c 25th November 2019
- Database Upgrade on Test
- Upgrade successfully registered by OH Business Lead
- Business Lead confirmed upgrade appeared to be ok
- HR interface tested and confirmed as functioning as expected
- Meeting with the business team resulting in project timescales being re-planned resulting
- UAT to be completed by 20/12/19
- Go-Live scheduled for 03/02/20
- ASTA updated to reflect new dates
- piccl prepared